Siemens PTI - Home
Siemens
 siemens.com  Home  Privacy & Legal 
 
 
 




 

Starting with Measured Flows

PSS™MUST uses a linearized DC load flow to calculate the incremental flow changes on monitored elements due to changes in generation, load, or topology. These incremental flow changes are added to the existing initial flows to obtain the final flows. Flow changes due to branch outages also require the initial flow on the line to be outaged. Therefore, initial flows are required for monitored branches and for branches to be outaged.

Initial flows can be obtained from another source other than the currently processed load flow case. PSS™MUST allows several options for obtaining initial flows:

  • Flows computed using DC load flow.

  • Flows computed using AC load flow.

  • Flows provided to PSS™MUST from an external database. Most likely, these flows will be obtained from the SCADA/EMS; hence, it is called the Energy Management System (EMS) Flows Method.

Traditionally, the first two options have been used in power system planning applications and are available in PSS™E. The EMS Flows Method provides a simple and efficient means to apply planning methods for ATC calculations in an operation or an operations-support environment. This approach is based on using a planner’s load flow case topology for incremental flow updates, and updated branch flow and branch status from the EMS environment.

Combining planning and on-line data brings many benefits for both planning and on-line applications. The main benefits of using a planner’s load flow case for EMS applications are:

  1. A planner’s load flow case will most likely have a better representation of external subsystems than in EMS cases. This allows, for example, to model the impact of through- system transactions on the study systems.


  2. The more sophisticated and flexible methods available in planning applications can be applied to EMS applications.


  3. If a utility does not have complete implementation of advanced EMS applications and cannot build on-line network topology, then the planning case can be used for incremental flow updates. If the SCADA/EMS cannot run the State Estimator (for example, due to observability problems), then directly measured flows can still be used as an intermediate solution.

Updating a planner’s load flow case to closely match real-time flows is a labor-intensive process. It can be accomplished only approximately as it is almost impossible to reconstruct external transactions, load levels, and generation dispatch in the external systems. Updating the planning model with real-time on-line flows brings the following benefits:

  1. Obtain much better estimates of initial flows.


  2. The EMS Flows Method can be efficiently combined with the PSS™MUST transaction scheduling system.


  3. With additional postprocessing, one can identify the source of differences between planning and on-line cases. Future developments are required in this area.

The use of EMS flows provides a simple alternative to an extremely complicated and time-consuming process of creating solvable on-line cases for OASIS TTC computations. The EMS Flows Method can be implemented within several weeks without solving complicated external systems observability problems.

The main drawback of using EMS flows is that it requires the manual update of the planner’s load flow case to accommodate topology changes. To apply the EMS Flows Method, the user has to provide the EMS flows for all monitored elements and all contingency branches to be processed.

Up