Siemens PTI Advises on the USTDA-Funded Feasibility Study of the Second Uruguay-Brazil Electrical Interconnection Project
Siemens
PTI recently completed an assignment entitled "Technical Assistance
for the Uruguay-Brazil Electrical Interconnection Project" (or,
the "Project"), funded by the United States Trade and Development
Agency (USTDA). The client was the National Directorate of Energy
and Nuclear Technology (DNETN) of the Ministry of Industry, Energy
and Mines (MIEM) of Uruguay. As part of this engagement, Siemens
PTI provided products and services from its three main areas of
business: consulting services, software products, and training
services. This clearly enabled the DNETN to take advantage of
Siemens PTI's entire portfolio of products and services in an
integrated manner
The assignment
started in January 2007 and was completed in June 2008. The Siemens
PTI project team included the following subcontractors: Taylor-DeJongh
(USA), TRC Global Management Solutions (USA), and PwC (Uruguay).
The Siemens PTI project members were Carlos Dortolina (Project
Manager), Dr. Ramón Nadira, Dr. Paloma De Arizón, and Dr. Carlos
Grande-Morán.
The Project
involves the construction of a second electrical tie line between
the countries of Uruguay and Brazil that will enable the further
exchange of electric power between these two countries. One of
the main challenges relative to this tie line is that the power
systems in these countries operate at different frequencies: Brazil
is a 60 Hz system while Uruguay operates at 50 Hz. As a result,
the Project is comprised of an AC transmission line (50 Hz) of
approximately 300 km in length on the Uruguayan side (from San
Carlos to Melo), a back-to-back converter station to be located
east of Melo in Uruguay, and a 90 km AC transmission line (60
Hz) from Melo to Candiota in Brazil. The Project is designed for
a nominal voltage of 500 kV and a transfer capacity of about 500
MW.
Siemens
PTI worked with the DNETN, the MIEM and UTE (the national electric
power utility in Uruguay) and specifically advised on the operational,
commercial and regulatory aspects of the Project. The scope of
work also included the provision of the Power System Simulator
for Engineering (PSS®E) software, computers to
run the software, and training in the use of PSS®E.
In combination, this engagement transferred to DNETN the technical
tools and knowledge necessary to independently assess future regional
electrical interconnection projects.
The consulting
activities of the engagement were organized into the following
seven tasks: (i) review and analysis of comparable interconnection
projects (case studies included tie-lines between countries as
well as interconnections between regions/grids in the same country);
(ii) assessment of regulatory, commercial and operational framework
(with the objective of identifying existing barriers to the implementation
of the interconnection project and recommending measures to eliminate
these barriers); (iii) identification and assessment of potential
sources of financing, led by Taylor-DeJongh, who examined the
issue of structures and options available for the financing of
the interconnection; (iv) preliminary review and assessment of
the environmental impacts of the project, led by TRC Global Management
Solutions; (v) identification and assessment of the key host country
developmental impacts, also led by TRC Global Management Solutions;
(vi) identification of potential US-based sources of supply; and
(vii) development of a project implementation plan. The objective
of this last task was to recommend a high-level step-by-step listing
of anticipated next steps necessary to transition the Project
to full implementation and operation (e.g., announcement of bidding,
selection of winning bidder, establishment of operating authority,
securing of funding from both Uruguay and Brazil, etc.). Included
in this Project Implementation Plan were the key steps attendant
to the raising of financing for the Project, and the suggested
timing and phasing of those steps.
In addition,
Siemens PTI delivered to the DNETN five computer workstations,
five copies of PSS®E with power flow, unbalanced fault analysis
and dynamic simulation (including extended term dynamics), five
copies of GMB (Graphical Model Builder), and three copies of PSS®MUST.
Training in the use of PSS®E was delivered in Montevideo, Uruguay,
by Dr. Paloma De Arizón (power flow and unbalanced fault analysis),
and Dr. Carlos Grande-Morán (dynamic simulation) in late 2007.
Finally,
it is important to mention that this assignment enjoyed considerable
visibility from the highest levels of government in Uruguay. Meetings
convened to discuss the results of the assignment were well attended,
and at times even the Minister and Vice-Minister of Industry,
Energy and Mines of Uruguay themselves participated in these meetings.
We hope that the potential benefits from this interconnection
project - which appear to be quite significant - can be fully
realized in the near future.
Download
document as .pdf
| Siemens Power Transmission
& Distribution, Inc., Power Technologies International
400 State Street | P.O. Box 1058 | Schenectady,
NY 12301-1058
Privacy
& Legal |
|