Understanding Financial Transmission Rights
Financial
Transmission Rights (FTRs), also known as Fixed Transmission Rights
(FTRs), Transmission Congestion Contracts (TCCs) or Congestion
Revenue Rights (CRRs), replace physical transmission rights in
centralized electricity markets. The FTR gives the holder the
financial equivalent of physical network capacity. Ignoring losses,
the effect of the FTR is to guarantee the holder that, for a predetermined
amount of energy, the holder’s price of energy at the point
of withdrawal will be the same as the price at the point of injection.
The FTR payoff is the difference in congestion between points
of injection (e.g., a remote generator) and withdrawal (e.g.,
a load center). FTRs are bought and sold in centralized electricity
markets for periods ranging from a month to several years.
A physical
transmission right gives the holder the right to use a particular
transmission line, or set of lines, to transfer energy from one
location to another. A financial right, in contrast, gives the
holder in one location the right to buy energy at the price of
another location. Consider Figure 1 for example. A physical transmission
right would give load at the East bus the right to use the transmission
line connecting the East bus with the West bus to transport energy
at a rate of up to 100 MW. A financial right would give load at
the East bus a guarantee that the price of the West bus will be
applied to 100 MWh per hour of energy consumed at the East bus,
regardless of how the transmission line is used. The difference
is negligible on the simple system shown in Figure 1 but it is
significant with real systems that are much more complex.

Figure 1 - Example System
The flow of energy over the individual lines of a transmission
system is governed by physical laws which have little regard for
ownership, contractual agreements, or property rights. Physical
transmission rights work well for radial systems where a unique
path can be identified between any two points. The concept of
physical rights tied to transmission ownership breaks down in
real systems which are not radial. Real systems have loops and
no unique path can be identified between every pair of points.
When multiple paths exist between two points, energy will flow
over all paths simultaneously. Thus physical rights can be more
of a fantasy than a reality. Financial rights, on the other hand,
will always work.
We
will use a simple system to illustrate the use of the FTR as a
hedging instrument to provide price certainty. Since the FTR is
a financial instrument, we must examine the settlement of energy
bought and sold to understand the value of the FTR. Initially
our system consists of Green Load at the East Bus and Green Generator
at the West Bus. East and West Buses are connected by a transmission
owned by Green Load. The initial system is illustrated in Figure
2. LMP, the locational marginal price of energy, is used in these
examples. LMP is the normalized (per MW) cost of supplying the
next small increment of load at a particular location while minimizing
the total production cost of energy. Relevant characteristics
of load, generation, and transmission are summarized below:
| Green
Generator |
|
|
| |
Size: |
|
110
MW |
| |
Marginal
Cost: |
|
$40/MWh |
| Green
Load |
|
|
| |
Size: |
|
95 MW |
| West-East
Transmission |
|
|
| |
Capacity: |
|
100
MW |
LMP at the
West Bus is $40. A small increment of additional load at the West
Bus would best be supplied by Green Generator at a cost of $40/MWh.
Similarly, LMP at the East Bus is $40. Green Generator would also
be the best (only) choice to supply a small increment of additional
load at the East Bus.

Figure 2 - Initial System
Settlement of the initial system is straightforward and is summarized
in Table 1. Green Load pays $3,800 for energy; Green Generator
collects $3,800 for energy. Everything balances and everyone is
happy.

Table 1 - Settlement of Initial System
Now suppose the system expands with the addition of Red Load and
Red Generator at the East Bus. Characteristics of these additions
are summarized below:
| Red
Generator |
|
|
| |
Size: |
|
10 MW |
| |
Marginal
Cost: |
|
$80/MWh |
| Red
Load |
|
|
| |
Size: |
|
10 MW |
The expanded
system and the least cost method of serving load in the expanded
system are shown in Figure 3. LMP at the West Bus is set by Green
Generator – additional load at the West Bus is best served
by Green Generator at a cost of $40/MWh. LMP at the East Bus is
set by Red Generator – additional load at the East Bus must
be served by Red Generator at a cost of $80/MWh. Therefore, there
is a significant price difference between West and East Buses.

Figure 3 - Expanded System
The energy settlement of the expanded system is shown in Table
2. Note three things. First, the minimum energy production cost
is attained when Green Generator supplies energy to both Green
Load and Red Load. Second, the LMP for Green Load has doubled
from $40/MWh to $80/MWh, even though Green Load has caused no
changes and owns more than enough transmission capacity to supply
its entire load from the cheaper Green Generator. Third, significantly
more money ($4,000) is collected from load than is paid to the
generators. The excess is called congestion rent and is the funding
mechanism for FTRs and the basis for making Green Load financially
whole.

Table 2 - Settlement of Expanded System
In lieu of its physical rights to the West-East Transmission,
Green Load is given an FTR for 100 MW. In accepting the FTR, Green
Load can no longer control access to the West-East Transmission,
but collects the congestion rent instead. The impact on Green
Load of the higher LMP is completely reversed by applying 95 MW
of the FTR to its own energy costs. Green Load pays $7,600/h for
energy but the 95 MW of FTR generates $3,800/h in congestion rent
and the net payment for energy is unchanged from the initial system.
The FTR has made Green Load financially indifferent to network
usage. Green Load’s net expenditure for energy in the expanded
(congested) system is the same as in the initial (uncongested)
system even though the price of energy at the Green Load location
has increased. The FTR provides Green Load with price certainty.
The remaining 5 MW of FTR generates $200/h in congestion rent
and can be thought of as a real-time payment from Red Load for
the use of the West-East Transmission. Red Load may prefer to
buy the remaining 5 MW of FTR from Green Load for a period of
time. This can be thought of as Red Load prepaying for use of
the West-East Transmission for that period of time.
Real power
systems are much more complex than the simple example above. However,
in real systems the FTR still protects the former holders of physical
transmission rights from the new price patterns and volatility
inherent in an LMP system. The FTR allows the system to be operated
in a least-cost manner which may involve new patterns of transmission
usage and congestion. Meanwhile, the former holders of physical
transmission rights are made financially indifferent to the change.
The interest
in FTRs extends beyond organizations that must make wholesale
purchases of electric energy. As seen above, some may value the
FTR as a congestion hedge to provide price certainty in lieu of
physical transmission rights. To others the FTR is viewed purely
as an investment opportunity. Regardless of how it is viewed or
valued, the FTR was designed as an alternative to physical transmission
rights. The easiest way to understand FTRs is in this context.
Download
document as .pdf
| Siemens Power Transmission
& Distribution, Inc., Power Technologies International
400 State Street | P.O. Box 1058 | Schenectady,
NY 12301-1058
Privacy
& Legal |
|