Protective Relaying
Control
and Protection
Power system
automation is performed by a variety of devices and subsystems
which can be hierarchized. Among these, the system human operators,
the automatic control subsystem and the relay protection subsystem
lie in the highest levels of the hierarchy. The automatic control
and relay protection subsystems monitor the power system behavior
on a permanent basis and automatically respond to system disturbances
(see Fig. 1).

Figure 1 - The protection system changes the power system
to minimize the impact of sever disturbance [1]
The control
system is comprised of generator voltage and speed controls, transformer
automatic tap changers, automatically switched reactors and capacitors,
FACTS, etc. These devices sensitively react to changes of the power
system state variables (commonly voltage and frequency) caused by
practically any disturbance. This system is intended to fix the
deviation of frequency and voltage caused by relatively minor disturbances,
like load connection/disconnection and normal maintenance switching.
The control system must be set in order to respond to a series of
pre-established design considerations. Power control engineers calculate
the control settings with the help of dynamic simulation
programs, like PSS®E.
Protection
Hardware and Philosophy
The protection
system is based on the philosophy of what has been traditionally
defined in the United States as Protective Relaying. Its
main elements are circuit breakers, instrument transformers, protective
relays and auxiliary devices (see Fig. 2). In medium and low-voltage
systems, fuses are also part of the protective hardware. Unlike
the control system, the protection system is designed to react primarily
to severe disturbances, as in the case of short circuits caused
by line insulation breakdowns during a lightning storm. The protection
system quickly reacts to disconnect the faulted element (power line,
transformer, generator, etc.). The automatic disconnection is achieved
with the circuit breakers, which open their high-duty power contacts
after receiving an order from the protective relays (see Fig. 2).
This disconnection -and the consequent extinguishing phenomenon-
is known as fault clearing. During the time the fault exists,
and immediately after its clearance, the power system experiences
a series of dramatic changes which may destroy individual components
or, in cases where the system dynamics are negatively impacted,
may lead to a major system dismembering and, eventually, to wide
area blackouts.
Protective
relays are low-voltage low-current intelligent devices which
detect the fault by measuring the current and/or voltage of
the system as reflected at the secondary side of specially
designed current and voltage transformers (see Fig. 2). The
measured phase currents and/or voltages generally have sufficient
information to feed a relaying algorithm (or mechanism) which
determines the breaker disconnection. Relays are configurable
and settable, so it is possible to use the same kind of line
protective relay to protect different types of lines; however,
there will be different relay settings for each particular
application. These relay or protection settings are
calculated according to a well established set of criteria.
The
protection system has to be: (a)sensitive, to detect
all faults; (b)fast, to minimize the damage that
faults may cause; (c)secure, to avoid operation for
non-fault or out of reach disturbances; (d)selective,
to strictly disconnect the minimum amount of service to clear
the fault; and (e)dependable, to ensure a reliability
close to 100%. When a short circuit occurs at some point in
the power system, one or more protective relays in the neighborhood
of the fault detect the fault; however, only those relays
that accomplish conditions (a) to (d) should be allowed to
disconnect their corresponding circuit breakers (see Fig.
3). A protection system that simultaneously accomplishes all
these characteristics is said to be coordinated.
Some relays, called backup relays, are set in a way
that their circuit breakers clear a fault in case there is
a failure in the operation of the relays originally intended
to clear that fault. This system backup type of design redounds
in reliability.
Protection
Coordination
When
all the relay designs, schemes and configurations of a protection
system are defined, the process of calculating the relay settings
in order to make such a system coordinated, as defined in
the previous paragraph, is commonly called protection
coordination. Engineers perform coordination studies
to assure that the protection system works according to the
aforementioned philosophy. Protection coordination -or relay
coordination- studies are traditionally carried out using
short circuit simulation programs and relay simulation programs.
In traditional methods, the relay settings are calculated
using rules of thumb based on engineers' experience: faults
are simulated over critical points of the system and the relays'
behavior is observed for each fault. If no coordination is
achieved at one attempt, the process must be repeated as many
times as needed until the protection system works according
to the coordination criteria. Engineers use simulation programs
(for example, the protection modules of PSS®SINCAL
used at Siemens PTI) as a support in the iteration process.
In some cases, due to the complexity of the system, the volume
of calculations involved is enormous; consequently, engineers
cannot find a satisfactory coordination solution for all the
relay settings. There are some (not many) automatic coordination
programs that help in this task [2]. Among other characteristics,
good automatic coordination programs have to be able to receive
practical inputs from the protection engineer in order to
adapt to any particular criteria and experience.
|

Figure
2 - Protection Hardware
A. Simplified scheme of line protection
B. Engineers "set" the relays
C. One-line diagram of (A)
|
As any
power system changes in short, medium and long term, engineers
have to re-calculate the optimum relay settings for each new
power system configuration. In other words, coordination studies
have to be performed on a regular basis to guarantee a proper
system performance. Relay coordination and all aspects related
to protective relaying represent a permanent source of work
for the protection engineering specialists.
Siemens
PTI and Protective Relaying
Siemens PTI - US has the computer tools and professionals
with the experience and skills needed to calculate relay
settings and produce the optimum results in protection
coordination studies as well as in all other aspects
related to protective relaying.
Siemens PTI offers the following consulting services
in the protection area:
-
Short-circuit calculation and fault analysis
-
Current transformer analysis and dimensioning
-
Dynamic and pseudo-static analysis and setting of
electromechanical, solid-state-analog and microprocessor-based
protective relays and schemes for transmission, distribution,
generation and industrial systems
-
Optimum setting calculation (coordination) of directional
overcurrent relays in transmission and subtransmission
systems
-
Distance relay setting calculation (coordination)
for high-voltage transmission lines
-
Protective relay setting calculation (coordination)
for power generators
-
Protective relay setting calculation (coordination)
for power transformers and other substation equipment
-
Utility distribution feeder protection coordination
using relays, fuses, sectionalizers, and reclosers
-
Industrial system protective relay setting calculation
(coordination)
- Protective
relay database design and maintenance
Protective
relaying is a wide field of knowledge. Everyday, new
applications, new situations, new problems to solve
and new criteria are born. The list displayed above
is just a subset of all the possibilities.
|
Figure
3 - One-line diagram view of the power system and
the protection system (only circuit breakers are shown).
Example: for a fault at F1, breakers 29 and 35 automatically
open in 5 cycles. If 29 failed to operate, then 31
and 26 should trip to clear the fault. This selective
mode of operation is part of the whole coordination
plan.
|
References:
[1] Pérez, L.; Venkatasubramanian, V.; Flechsig, A., "Modeling
the Protective System for Power System Dynamic Analysis,"
IEEE Transactions on Power Systems, vol. 9, no.
4, Nov. 1994.
[2] Pérez, L.; Urdaneta, A., "Optimal Coordination of
Distance Relays Second Zone Timing in a Mixed Protection
Scheme with Directional Overcurrent Relays," IEEE
Transactions on Power Delivery, vol. 16, no. 3, Jul.
2001. |
Download
document as .pdf
| Siemens Power
Transmission & Distribution, Inc., Power Technologies
International
400 State Street | P.O. Box 1058 | Schenectady,
NY 12301-1058
Privacy
& Legal |
|
|