Colstrip 500 kV Power Transfer Capabilities Studied
Overview
The transmission owners of the Colstrip 500 kV Transmission System
and the Bonneville Power Administration wanted to evaluate the
ability of their existing 500 kV transmission assets to support
additional power transfers from Montana to the Pacific Northwest.
This study was initiated in anticipation of significant new generator
interconnection requests and transmission requests. One benefit
of this study was the identification of the level of power transfers
that could be supported from existing facilities prior to the
need to study, permit, design and construct new transmission.
Siemens PTI conducted this study in 2009.
The participants
in this study were NorthWestern Energy (Butte, MT); PacifiCorp
(Portland, OR); Avista Corporation (Spokane, WA); Portland General
Electric Company (Portland, OR); Puget Sound Energy (Bellevue,
WA) and the Bonneville Power Administration (Portland, OR).
The goals
of the study were to determine the following:
- What transmission
upgrades to the existing 500 kV infrastructure are necessary
to allow increased power transfers injected in Montana and offloaded
in central Washington?
- What is
the incremental increase in transfer capability for discrete
investment levels in infrastructure upgrades?
- What is
the ultimate capability of the existing 500 kV infrastructure?
The study
participants identified three locations for possible injections
of power to the existing system: Colstrip, Broadview, and Townsend.
Further, the participants specified that two generation technologies
were of interest: wind and thermal. In combination with three
seasonal scenarios representing two unique flow patterns and three
types of technical assessments, a total of 36 unique evaluations
were performed. The basic study system is shown below:

Figure 1 - Colstrip / West 500 kV Transmission System
Voltage
Collapse Evaluation
The first evaluation completed was a PV voltage collapse evaluation.
This analysis established a distinct upper limit. Although more
limiting constraints in subsequent analyses are possible, exceeding
the voltage collapse limit would have required major system improvements,
and this helped to bound the stability assessments that followed.
The PV functionality
of PSS®E is ideally suited for this evaluation, because it
evaluates a range of injection levels, and runs contingencies
at each internal level of the scaling process of the analysis.
The principal
information garnered from the voltage collapse evaluation was
whether the thermal capability of the conductor and bus work was
greater than or less than the voltage collapse limits. Naturally,
the hope was that the voltage collapse limit was at a higher flow
level than the thermal capabilities of the major infrastructure,
leaving open the possibility that the full thermal capability
of the conductor and bus could be used to support power transfers.
Steady-State
Contingency Evaluation
Although both the PV and contingency evaluation are both fundamentally
steady-state evaluations, these reveal slightly different system
characteristics. Whereas the PV analysis identified a maximum
steady-state capability, the contingency evaluation provided insight
into generally less severe criteria violations that also needed
to be mitigated, such as high or low voltage levels or overloads.
The PV and
dynamic stability analyses focused efforts on identifying ultimate
system capability, based on taking a few severe contingencies
to their points of failure, regardless of any equipment overloads
or underlying low voltage concerns that may occur during the process
of stressing the system to its voltage collapse or dynamic limits.
The contingency analysis did not change the system’s stress
level, but included a comprehensive set of contingencies at the
limits established by the PV or dynamic studies.
The added
value, therefore, of performing the steady-state contingency analyses
was that a clearer picture emerged of the equipment upgrades and
supplemental voltage support devices needed during less severe
contingency conditions. This, in turn, resulted in better cost
estimates. The steady-state contingency analysis was the mechanism
by which the need for an augmenting Static VAR Compensator for
some injections and some flow patterns was determined.
Dynamic
Stability
The final type of evaluation performed was dynamic stability.
The intent of this study was to determine if the injection points
and flow pattern scenarios were limited by stability concerns.
The study system relies heavily on established remedial actions
to assure dynamic stability, and additional transfers did not
reduce this reliance, particularly during double circuit contingencies
of the 500 kV system. The study system includes double circuit
500 kV towers, thereby requiring double circuit contingency evaluations.
Cost
Estimates
After completing all technical analyses, Siemens PTI developed
rough order-of-magnitude cost estimates to incrementally increase
transfer capability on the study system. Basic unit costs were
utilized, thereby making the cost estimates suitable for comparison
purposes only. A key factor in developing the cost estimates was
Siemens PTI’s knowledge and experience with Thyristor-Controlled
Series Capacitors (TCSC).
Siemens PTI
was able to develop some preliminary design parameters, and develop
cost estimates from the preliminary design. Complimenting the
series capacitor cost estimates was rough order-of-magnitude cost
estimates of various other infrastructure upgrades.
Siemens PTI
takes pride in providing independent consulting advice to clients,
rejecting all forms of favoritism. In this study, however, our
association with Siemens as an equipment manufacturer, and Siemens
PTI’s knowledge of leading-edge power electronics, provided
valuable insight in forging the preliminary cost estimates.
Conclusion
Given today’s asset limitations and ever-increasing need
for power transfer, studies like this provide important information
regarding current and future transmission system capability. Through
this study, the Consultants at Siemens PTI provided preliminary
insight into the challenges and upgrade magnitudes necessary to
support additional power transfers on the 500 kV system from Colstrip
in the east to eastern Washington in the west.
Download
document as .pdf
| Siemens Energy,
Inc., Power Distribution, T&D Service Solutions
Siemens Power Technologies International
400 State Street | P.O. Box 1058 | Schenectady,
NY 12301-1058
Privacy
& Legal |
|