PSS®E
Test System for Voltage Collapse Analysis
Introduction
Voltage collapse is one of the major limitations in modern transmission
systems. Quite often it is the most limiting factor preventing
further increases in power transfers over existing transmission
lines and interfaces.
PSS®E
contains several activities that help the analysis of voltage
collapse issues and the investigation of potential mitigation
solutions after a voltage collapse condition is identified.
The objectives
of this paper are:
- provide
a small system susceptible to voltage problems;
- describe
the different voltage collapse conditions observed in this test
system; and
- present
the PSS®E tools for investigating voltage collapse problems.
This paper
presents a relatively small system for the analysis of voltage
collapse issues. It is based on the 1979 IEEE Reliability Test
System [1], which was extended to represent multi-area systems
in the 1996 version of the IEEE Reliability Test System [2]. However,
the test system and associated data presented in this paper is
related to the so-called “one area RTS-96” system
[2], which is equivalent to the 1979 Reliability Test System [1].
Changes
to the IEEE Reliability Test System
Several modifications were introduced in the power flow data of
the original 1979 IEEE Reliability Test System to make it more
suitable for voltage stability/voltage collapse analysis. These
changes were introduced to highlight different aspects of the
problems related to voltage control and reactive power compensation.
The following
changes were introduced by Siemens PTI:
- The synchronous
condenser at bus 114 was replaced by a static VAR compensator
(SVC) with the same nominal range (–50/+200 MVAr). In
practice, the reactive power output of this device becomes voltage
dependent and its maximum reactive power output is severely
reduced under low voltage conditions.
- The shunt
at bus 106 was replaced by an SVC with a range of (-50/+100
MVAr). This change introduces one additional voltage control
equipment that is quite important. This SVC is a key component
in the proposed system data and is usually required to avoid
voltage collapse during dynamic simulations.
- The step-up
transformers of generators and SVCs are explicitly represented
in the case, assuming 5 tap positions and no OLTC. The generators
are connected to the low voltage bus, assumed to be
18 kV for all units. All generators remotely control the voltage
at the high voltage side on their GSU in the power flow, while
the SVCs control local (terminal) voltage.
- All other
transformers in the case are represented as +/- 10% OLTC transformers
with 33 steps (0.625% per step). Tap changers are located on
the high voltage side of the transformer. The OLTC controls
the voltage at the low voltage side bus.
- The loads
are no longer directly connected to the 138 kV or 230 kV buses.
Step-down transformers to 13.8 kV with an OLTC controlling their
low voltage side are introduced with an estimated 15% reactance
on an MVA base calculated by rounding up to the nearest multiple
of 50 MVA 110% of the load apparent power.
- The branch
between buses 107 and 108 was converted to a double circuit
to avoid islanding a group of buses under N-1 contingencies.
- Line reactors
were added to compensate the charging of the long underground
cable between buses 106 and 110.
Table 1 contains
the dimensions of the resulting power flow case in PSS®E.
Figure 1 presents the single line diagram of the system. Table
2 shows the total generation and load in the case.

Table
1 – Resulting Dimensions of the Power Flow Case

Table 2 – Total Generation and Load in the System

Figure 1 – One Line Diagram of the Resulting System
Power Flow Solution
The power flow solution was adjusted using the PSS®E Optimal
Power Flow (OPF) to bring all voltages within normal range (1.05
to 0.95 pu). This OPF solution modified tap positions and generator
scheduled voltages as compared to the original data of the IEEE
Reliability Test System.
There
are three N-1 contingencies in the HV transmission system (230
kV and 138 kV networks) that result in non-convergent power flow
solutions, as shown in Table 3. The outage of the line between
buses 107 and 108 results in the islanding of 5 buses. To avoid
this difficulty, the branch between buses 107 and 108 was converted
to a double circuit.

Table 3 – Non-Convergent Power Flow Solution of Contingencies
The
outage of the underground cable between buses 106 and 110 is probably
the worst contingency. This cable has a large charging (about
250 MVAr) and no line reactors are connected to it in the original
data. Line reactors were added at each terminal of the cable (75
MVAr in each end). This change results in a more realistic system,
taking into consideration the usual requirement for such line
reactors due to overvoltages during energization and load rejection
conditions. It should be noted that these reactors are automatically
disconnected in PSS®E when the cable is switched off.
PV
and QV Analyses
Figure 2 presents the QV plots calculated for bus 110 for the
base case and some of the critical contingencies.
The
reactive power margin in the base case is 116 MVAr, dropping to
just 10 MVAr for contingency #4 (230 kV circuit between buses
112 and 123). Voltage collapse conditions are identified for contingency
#10 (230 kV circuit between buses 115 and 124) and contingency
#30 (138 kV circuit between buses 106 and 110).
It
should be noted that the reactive power deficiency for contingency
#10 is greater than 150 MVAr and the minimum of the associated
QV curve is associated with bus voltage greater than 1.0 pu. The
QV curve associated with contingency #30 is incomplete, since
the power flow solution did not converge for voltages below 0.97
pu.
These
QV results were obtained using a full Newton power flow solution
and the non-divergent power flow solution in PSS®E. The transformer
taps are locked during the contingency calculation, but the switched
shunts with continuous control (SVCs) are allowed to respond.
The
PV analysis considered generation to load transfers from the 230
kV to the 138 kV networks. In other words, the generation connected
to buses 113, 114, 115, 116, 118, 121, 122 and 123 is increased,
with the additional power being transferred to the loads connected
to buses 1101, 1102, 1103, 1104, 1105, 1106, 1107, 1108, 1109
and 1110.
It
should be noted that the additional generation available on the
230 kV system (Pmax – Pgen) is about 100 MW. Transfers greater
than 100 MW imply a disregard for the data associated with maximum
power output of the generation units. Furthermore, since the ratings
for the generator step-up transformers match the generator MVA
capability, the overload of the generators also imply an overload
of the step-up transformers.
Figure
3 presents some of the calculated PV plots. These plots correspond
to the voltages at the 138 kV buses 106 and 110, as well as the
voltages at the 13.8 kV load buses 1106 and 1110. The maximum
transfer calculated for the base case is slightly under 100 MW.
No incremental transfer is possible for contingency #30 (see the
QV results), as well as for contingency #6 (outage of the 138
kV circuit between buses 114 and 116) and contingency #10 (outage
of the 230 kV circuit between buses 115 and 124). Contingency
#4 resulted in a maximum incremental transfer of just 10 MW.

Figure 2 – QV Plot for Bus 110

Figure 3 – PV Plots for Transfers from the 230 kV to the
138 kV Networks
Dynamic
Simulation Data
The dynamic data originally proposed for the Reliability Test
System consists of classical generator models for all generators,
which is inadequate for voltage stability/voltage collapse analysis.
Therefore, typical models are proposed for all the elements as
described in the following sections.
Generators
The units identified as hydro turbines in the original Reliability
Test System are represented by the GENSAL salient pole machine
model. All other units are thermal units and are represented by
the GENROU round-rotor machine model.
The
inertias were set to the values originally proposed, even though
they are probably on the lower end of the typical range for similar
units. This lower inertia might imply that the system will be
more susceptible to angular instability (loss of synchronism)
and poorly damped oscillations than would be expected if more
realistic inertias are considered. Additional simulations will
be required to quantify this effect and determine how important
it is to the overall simulation results.
All
other parameters are representative of generation units of comparable
MVA ratings.
Excitation Systems
Three different excitation system models were used. The IEEET1
and EXAC1 models correspond to AC rotating exciters, while the
SCRX model represents a bus-fed static exciter. The parameters
for these excitation systems provide a reasonable, representative
response for these equipment.
The
limits are set in such way as to limit the ceiling (maximum field
voltage) to be around twice the rated (full load) field voltage.
The resulting response ratios are above 1.0, with the exception
of the generator at bus 30123. The relatively high ceiling in
these excitation systems results in a responsive voltage control,
consistent with modern excitation systems.
Maximum Excitation Limiters
The over-excitation limiter (OEL) model MAXEX2 was applied for
all generators. This model corresponds to an OEL that acts at
the voltage reference of the excitation system with an inverse
time characteristic. The rated value for the field current was
calculated in PSS®E considering the generators at full power
output with 0.9 power factor. Changes to the generator model parameters,
particularly the saturation characteristics and synchronous reactances,
would affect the rated field current and would require adjustments
to the corresponding OEL model.
Turbine/Speed
Governors
Only a few generators have a turbine/speed governor model. Those
machines without such a model are simulated with constant mechanical
power. There is a limited amount of reserves in the case, so the
simulation of large imbalances between generation and load should
be avoided, since there is a significant risk of large frequency
excursions and even the inability of the simulation model to control
frequency.
The
hydro turbines are represented by the model HYGOV, while the IEEEG1
model is used for the steam units. It should be noted that the
parameters for the steam turbines consider a tandem-compound unit
with a reheater [3].
Static
VAR Compensators
The power flow case contains two static VAR compensators (SVC)
represented as switched shunts with continuous control. The first
one is connected to bus 10114 and is rated –50/+200 MVAr.
The other one is rated –50/+100 MVAr and is connected to
bus 10106.
The
PSS®E model CSSCST is used to represent the dynamic response
of these devices. The steady state gain K is set at 150 pu/pu,
but is provided in the PSS®E model in Mvar/pu, resulting in
the gains 37,500 (250 x 150) and 22,500 (150 x 150) for these
dynamic models. The thyristor bridge is represented by a first
order lag, with a time constant T5 = 30 ms. The time constant
T3 was calculated for each SVC so a reasonable closed-loop response
(adequate phase margin) is obtained. The methodology for the calculation
of T3 is described in [4, 5].
The
limits Vmax and Vmin are entered as zero in the CSSCST dynamic
model, so the voltage setpoint provided in the power flow data
is used. The voltage override capability provides a discontinuous
control for large voltage deviations, forcing the SVC output to
its limits when the voltage error is larger than Vov = 0.5 pu.
Tap
Changers
The representation of the effect of OLTC transformers is particularly
important for the analysis of slow voltage collapse phenomena.
This model is usually associated with longer term dynamic simulations,
up to several minutes after fault clearing.
All
transformers represented with on-load tap changers in the power
flow have the PSS®E dynamic model OLTC1 in the dynamic setup.
This model does not contain any differential equations (state
variables); it considers an initial delay for the first tap change
of 30 seconds, with a 1 second delay in the switching action and
5 seconds delay before consecutive tap changes are allowed. It
should be recognized that this is quite fast and probably faster
than most practical settings, with the effect of the OLTC becoming
evident with simulations lasting just one to two minutes after
fault clearing.
Load Recovery
Similarly to the OLTC transformers (and associated with it), the
recovery of the load demand to the pre-disturbance levels is important
for the analysis of slow voltage collapse phenomena. The representation
of such phenomena is also associated with longer term dynamic
simulations, up to several minutes after fault clearing.
Load
recovery to a constant MVA characteristic is represented in PSS®E
by the family of models EXTLxx. This model provides separate time
constants for the recovery of the real and reactive parts of the
load. The EXTLAL model was used to apply this characteristic to
all loads in the system. The gains Kp and Kq are set to 5%, resulting
in a recovery to constant MVA in a few minutes after the fault
clearing. Again, this is probably faster than what is observed
in practice. The use of such values simply makes the effect more
evident and more pronounced in the overall system response, which
is desirable in a test system.
Complex
Load Model
A different kind of voltage collapse is associated with the stalling
of induction motors due to low voltages during the fault, resulting
in inadequate voltage recovery after fault clearing or even voltage
collapse. This is sometimes called short-term voltage collapse
to differentiate it from the slower (long-term) phenomena associated
with OLTC action and load recovery to constant MVA characteristics
[6, 7].
This
fast voltage collapse problem can be investigated in PSS®E
with the use of the complex load model. The CLODAL version of
the model applies the same load characteristics to all loads in
the system. The following load composition is proposed:
- 15%
of large induction motors (industrial motors);
-
35% of small induction motors (air conditioning);
-
2% of transformer excitation current;
-
15% of discharge lighting;
-
5% of constant MVA load;
-
remaining load (28%) represented as 100% constant current for
the real part and 100% constant admittance for the reactive
part; and
-
5% reactance (on load MW base) in the step-down transformer.
Dynamic
Simulation Results
In order to demonstrate the key features of the proposed test
system regarding voltage collapse/voltage stability issues, the
following section presents the results of some of the simulations
performed.
PSS®E
activities ESTR/ERUN and GSTR/GRUN were applied to make sure that
the excitation systems and speed governors models resulted in
properly tuned responses, compatible with the expected performance
of these equipment.
The
key test regarding the control tuning of excitation systems is
the open circuit step test. Figure 4 presents the response of
the EXAC1 model to a 2% step change in voltage reference. It can
be seen that the voltage regulator provides a fast response with
minimal overshoot. Similarly, Figure 5 and Figure 6 present the
responses obtained with the IEEET1 and SCRX models, respectively.
The
test for the speed governor response consists of the generator
feeding a constant MW load in isolated mode. A sudden change in
the load demand is applied and the speed governor reacts to modify
the mechanical power output. Typically, the simulation is initialized
with the generator power output at around 60% of the generator
MVA rating and the load demand is increased to 70% (10% step).
Figure
7 shows the response of one of the generators with the IEEEG1
governor model. It can be seen that frequency (speed) reaches
a new steady state in about 15 seconds, without restoring frequency
to its nominal value. The steady state frequency deviation in
this simulation is proportional to the steady state droop in the
model and the magnitude of the step change in load.
Figure
8 depicts the response of the hydro units (HYGOV model), which
is characteristically slower and depends on the settings for the
transient droop.

Figure 4 – Open Circuit Step Response (2% Step in Voltage
Reference) for EXAC1 Exciter Model

Figure 5 – Open Circuit Step Response (2% Step in Voltage
Reference) for IEEET1 Exciter Model

Figure 6 – Open Circuit Step Response (2% Step in Voltage
Reference) for SCRX Exciter Model

Figure 7 – Speed Governor Response Test for IEEEG1 Model

Figure 8 – Speed Governor Response Test for HYGOV Model
Test Case A – 250 MVAr Reactor Connected to Bus
101
This simulation is performed with the initial dynamic data setup
for the proposed PSS®E voltage stability test system. This
dynamic setup contains the following models:
-
synchronous generators (GENROU or GENSAL models);
- excitation
systems (IEEET1, EXAC1 or SCRX models);
- turbine/speed
governors (HYGOV or IEEEG1 models);
- over-excitation
limiters (MAXEX2 model); and
- transformer
OLTC (OLTC1 model).
It is important
to note that, at this point, the loads are represented as 100%
constant current for the real part and 100% constant admittance
for the reactive part. The load reset characteristic (EXTLAR model)
and the complex load model (CLODAL) are not applied in this simulation.
Furthermore,
the SVCs are not yet included in the dynamic simulation. The reactive
shunt compensation at buses 10114 and 10106 are held at their
pre-disturbance values given by the power flow solution.
This test
case highlights the response of the over-excitation limiter (OEL)
at machines 3 and 4 connected to bus 101, as well as the OLTC
response.
Figure 9
presents the response of the generator at bus 30101, showing real
and reactive power output (in pu on 100 MVA), terminal voltage,
generator field voltage and the output of the MEL.
It can be
seen that the OEL becomes active near t = 50 seconds and reduces
the generator field voltage, resulting in a reduction in reactive
power output and terminal voltage.
Poorly damped
electromechanical oscillations can be observed in the power output
of the unit. Properly tuned stabilizers would be required to improve
damping, since some contingencies might lead to instability. This
was not investigated at this time.
Figure 10
shows the response of the load connected to bus 1101, where the
effect of the OLTC model is clearly seen. The load is represented
as 100% constant current for the real part and 100% constant admittance
for the reactive part and the load demand recovers to almost its
initial value as the tap changes bring voltage closer to its initial
value.

Figure 9 – Response of Generator at Bus 30101
Figure 10 – Response of Load at Bus 1101
Test Case B – Outage of the Cable between Buses
106 and 110
This simulation corresponds to the critical contingency identified
in the steady state analysis. The only disturbance is the trip
of the cable (together with the line-connected shunt reactors)
without any fault.
The
power flow solution did not converge for this contingency and
the QV analysis shows that this outage corresponds to a voltage
collapse condition.
Figure
11, Figure 12, Figure 13, and Figure 14 present the voltages at
buses 106 and 1106, as well as the real and reactive demand of
the load at bus 1106. Four different simulations of potential
remedies were performed:
-
SVC at bus 10106 ( -50/+100 MVAr) without load reset characteristic
(black curve);
-
SVC at bus 10106 ( -50/+100 MVAr) with load reset characteristic
(red curve);
- shunt
at bus 10106 blocked at its initial value in power flow (no
dynamic model for SVC) without load reset characteristic (blue
curve); and
-
shunt at bus 10106 blocked at its initial value in power flow
(no dynamic model for SVC) with load reset characteristic (magenta
curve).
The loads
are still represented as 100% constant current for the real part
and 100% constant admittance for the reactive part. The load reset
characteristic is added to the PSS®E setup (model EXTLAL),
and this model would eventually bring the loads back to their
initial (pre-disturbance) values (MW and Mvar).
It should
be noted that the selected values for the gains KP and KQ (5%)
in the EXTLAL model are quite high, resulting in an artificially
fast load recover to constant power characteristics (few minutes).
Actual recordings of load characteristics indicate that this is
a much slower phenomenon, spanning many minutes.
Similarly,
the dynamic response of the SVCs is simulated by adding the model
CSSCST to the PSS®E dynamic simulation setup. The dynamic
response of the SVC is critical to avoid a voltage collapse condition
around bus #106.
In fact,
the SVC response combines with the OLTC response to bring the
voltage at the load bus #1106 to a higher value than the initial
(pre-disturbance) condition. Since the load is modeled with a
voltage dependence characteristic, the load demand becomes greater
than the initial (steady-state) value and the load reset model
ends up reducing the load demand.
On the other
hand, when the SVC is blocked (shunt is held constant at its initial
value given by the power flow solution), the voltages at buses
#106 and #1106 do not recover. Without the load reset characteristic,
these voltages stabilize at around 0.9 pu due to the associated
reduction in real and reactive power load demand. When the load
is reset to its pre-disturbance power demand, voltages decrease
even further and stabilize just above 0.8 pu.
Since this
is a slow voltage collapse condition, it is conceivable that mechanically-switched
capacitor banks could be applied instead of a much more expensive
SVC. However, the SVC will also play a fundamental role in the
fast voltage collapse condition shown in the next section.

Figure 11 – Voltage at 138 kV Bus #106

Figure 12 – Voltage at 13.8 kV Load Bus #1106

Figure 13 – Real Power Demand of Load at Bus #1106

Figure 14 – Reactive Power Demand of Load at Bus #1106
Test Case C – Three-Phase Fault at Bus 106
This simulation also corresponds to the critical contingency identified
in the steady state analysis; but this time the cable is tripped
to clear a three-phase short circuit at bus #106, cleared after
6 cycles (100 ms).
Figure
15, Figure 16, Figure 17, and Figure 18 present the voltages at
buses 106 and 1106, as well as the real and reactive demand of
the load at bus 1106. Four different simulations were performed:
- SVC
at bus 10106 ( -50/+100 MVAr) without dynamic load model CLODAL
(black curve);
-
SVC at bus 10106 ( -50/+100 MVAr) with dynamic load model CLODAL
(red curve);
- shunt
at bus 10106 blocked at its initial value in power flow (no
dynamic model for SVC) without dynamic load model CLODAL (blue
curve); and
-
shunt at bus 10106 blocked at its initial value in power flow
(no dynamic model for SVC) with dynamic load model CLODAL (magenta
curve).
The complex
load model provides an easy way to investigate the influence of
the load model in the dynamic simulation and, in particular, the
effect of induction motors in voltage collapse/voltage recovery.
The CLODAL
model is added to the original PSS®E dynamic simulation setup
and it replaces the original load model (100% constant current
for real part and 100% constant admittance for reactive part).
It should be noted that 50% of the load demand is now associated
with induction motors.
As previously
stated, the dynamic response of the SVC is critical to avoid a
voltage collapse condition around bus #106, caused by the increase
in reactive power demand due to stalling induction motors. This
is a fast dynamic phenomena and, in this case, the control capability
of the SVC is required to avoid sluggish voltage recovery and
the potential of load disconnection due to sustained low voltages.
Figure 19 presents the SVC output admittance for the cases with
and without the complex load model (induction motors). Note that
the SVC stays at its maximum limit for almost 2 seconds when the
induction motors are represented. This reactive power support
is fundamental to enable the reacceleration of the motors.
When the
SVC is blocked and the induction motors are present, the voltages
at buses #106 and #1106 do not recover, staying below 0.6 pu,
which would lead to motor tripping and possibly system shutdown.
Figure 15 – Voltage at 138 kV Bus #106

Figure 16 – Voltage at 13.8 kV Load Bus #1106

Figure 17 – Real Power Demand of Load at Bus #1106

Figure 18 – Reactive Power Demand of Load at Bus #1106

Figure 19 – SVC Output Admittance
Conclusions
This paper presented a relatively small test system with documented
voltage collapse/voltage stability problems.
These
problems are identified using steady state tools (power flow,
contingency analysis, and PV/QV analysis) and the dynamic simulation
capability in PSS®E. In particular, the test system provides
an example of the use of dynamic simulation models that are quite
specific for the analysis of voltage collapse problems.
This
test system will be incorporated in the example systems distributed
with PSS®E. Meanwhile, the data is available in PSS®E
rev. 31 format by request to the PSS®E support.
| References |
| [1] |
Reliability
Test System Task Force of the Application of Probability Methods
Subcommittee – “IEEE Reliability Test
System”, IEEE Trans. on PAS, vol. 98, no. 6,
Nov./Dec. 1979, pp. 2047-2054. |
| [2] |
Reliability
Test System Task Force of the Application of Probability Methods
Subcommittee – “The IEEE Reliability
Test System – 1996”, IEEE Trans. on PWRS,
vol. 14, no. 3, Aug. 1999, pp. 1010-1020. |
| [3] |
Task
Force on Overall Plant Response – “Dynamic
Models for Steam and Hydro Turbines in Power System Studies”,
IEEE Trans. on PAS, vol. 92, no. 12, Dec. 1973, pp.
1904-1915. |
| [4]
|
Siemens
PTI – “PSS®E Rev. 31 Program Application
Guide”, vol. II, section 15.5.
[5] Rodolfo Koessler – “Dynamic Simulation of
Static Var Compensators in Distribution Systems”, IEEE
Trans. on PWRS, vol 7, no. 3, Aug. 1992, pp. 1285-1291. |
| [6] |
IEEE/CIGRÉ
Joint Task Force on Stability Terms and Definitions
– “Definition and Classification of Power System
Stability”, IEEE Trans. on PWRS, vol. 19, no.
2, May 2004, pp. 1387-1401. |
| [7] |
Badrul
H. Chowdhury and Carson W. Taylor – “Voltage
Stability Analysis: V-Q Power Flow Simulation Versus Dynamic
Simulation”, IEEE Trans. on PWRS, vol. 15,
no. 4, Nov. 2000, pp. 1354-1359. |
Download
document as .pdf
| Siemens
Energy, Inc., Power Distribution, T&D Service Solutions
Siemens Power Technologies International
400 State Street | P.O. Box 1058 | Schenectady,
NY 12301-1058
Privacy
& Legal |
|