North East Power System (NEPS) Energization Study
Synopsis
The main objective of switching studies is to make sure that the
transmission system can be energized in a secure manner that guarantees
that the system equipment can withstand the overvoltages due to
the corresponding maneuvers. These studies generally include steady-state
evaluation of every energization step, electromagnetic transient
studies of switching of selected topologies (most critical cases)
and verification of the absence of sustained overvoltages due,
for example, to self-excitation of generators during load rejection
events. Siemens PTI has recently conducted such studies on the
Uzbekistan-Afghanistan 220 kV interconnection, for Advanced Engineering
Associates International (AEAI). This interconnection was energized
weeks later and is now supplying power to several communities
in northern Afghanistan. This article summarizes the results of
the study completed to verify the proposed energization procedure.
The North
East Power System (NEPS) is a 220 kV grid system, built in Afghanistan
to import power from neighboring Uzbekistan. An overview of the
NEPS is shown in Figure 1. Power will be transported to the main
load center in Kabul and to the various communities along the
way. The interconnection is radial from the Surkhan 220 kV bus
and supplies load that is isolated from the rest of the Afghanistan
power system.
Steady-State
Evaluation
The energization procedure provided by AEAI was reviewed and modified
in order to preserve the system integrity while serving the maximum
load in the Kabul region. The recommended energization sequence
has 18 steps, and is described in Table 1. The amount of total
load connected was less than that originally proposed to maintain
acceptable voltage levels. Several sensitivity cases were also
performed in order to maximize the power transfer to Kabul.

Figure 1 - North East Power System (NEPS)
Table
1 - Recommended Energization Sequence

Load
Rejection Study
The main objective of the load rejection study is to evaluate
the possible sustained overvoltages in the system due to the switching
events. Surkhan generator is modeled as a conventional generator
with governor and excitation, as no additional data is provided
by the client. Table 2 shows the load rejection scenarios and
the associated system condition. The studies are performed using
the PSS®E transient stability program. The system is stable
for all switching events considered in the study. However, for
the loss of the Chimtalah transformer and reactor, the Pul-e-Khumri
and Chimtalah 220 kV buses experience high voltages. The loss
of reactor may activate the overvoltage protection at Chimtalah
substation.
Table 2 - Load Rejection Study Results

Electromagnetic Transient Evaluation
The objective of this study is to verify the adequacy of the line
insulation during the energization process. The switching of 220
kV lines, interconnecting the Surkhan substation to the Chimtalah
substation, is simulated, as energization of 220 kV lines represents
the worst scenario from a transient overvoltage point of view.
The study is performed using MicroTran (EMTP program). Statistical
(uncontrolled) switching is simulated for the considered switching
sequences, and voltages at the 220 kV buses are observed. The
voltage at the Chimtalah 220 kV bus for the loss of reactor is
shown in Figure 2. For the installations of voltage levels 245
kV and lower, the Basic Insulation Level (BIL) is the most demanding
condition. The results show that the maximum instantaneous overvoltage
is 2.9 pu (502 kV crest) and the BIL for the 220 kV substations
is 1050 kV, with a minimum of 950 kV for some power transformers.
Therefore, as per the results of this study, the equipment insulation
should withstand the switching overvoltages. The sustained overvoltage
levels after the line energization maneuver is simulated are under
1.1 pu, and are consistent with the steady-state simulations described
above.

Figure 2 - Voltage at Chimtalah Substation for the Loss of Reactor
Conclusion
An energization/switching study involves steady-state evaluation
of each switching step, transient evaluation of switching of critical
lines, and verification of the absence of sustained overvoltages
due to load rejection. The results of a study of this type, performed
on the Uzbekistan-Afghanistan 220 kV interconnection, have been
presented in this article. The proposed energization sequence
was modified based on this study. The load rejection study results
show that the system is stable for all switching actions considered
in the study, except for a sudden loss of reactor at Chimtalah,
which may trigger the overvoltage protection. The transient overvoltage
evaluation of line switching indicates that the 220 kV lines have
sufficient insulation to withstand the overvoltages during the
switching process. This line was successfully energized at the
end of April and is supplying power to Afghanistan.
Download
document as .pdf
| Siemens Energy,
Inc., Power Distribution, T&D Service Solutions
Siemens Power Technologies International
400 State Street | P.O. Box 1058 | Schenectady,
NY 12301-1058
Privacy
& Legal |
|