The Growth of Siemens PTI US in Medium Voltage Distribution
Network Solutions in the Past Year has been Remarkable, Thanks
to PSS®SINCAL
Siemens
PTI US, and our PSS®E product suite, are widely recognized
as a world leader in steady-state and dynamic studies for power
transmission systems. We are also well equipped with the consulting
expertise and software tools required to perform FACTS and HVDC
studies.
The success
of Siemens PTI US after our acquisition by Siemens in 2005 can’t
be discussed completely without mentioning our work in medium
voltage distribution studies. Thanks to PSS®SINCAL, we have
grown enormously in this area, domestically as well as internationally.
For distribution and industrial clients, the addition of PSS®SINCAL
modeling and simulation capabilities has enabled us to expand
our services offered from the Houston, Texas regional office.
The purpose
of this article is to bring to light some accomplishments of Siemens
PTI US in the field of medium voltage distribution network planning
studies in the past year. In addition to transmission related
projects, consultants at the Houston, Texas, regional office have
been actively involved in these distribution planning studies.
Following is a summary of projects which we successfully completed
this past year using PSS®SINCAL.
Analysis of Kabul Distribution System using PSS®SINCAL
This study of the Kabul, Afghanistan, distribution system (a balanced
three-phase network) was conducted for both short term (one year
out) and medium term (three or more years), and also included
our estimation of the investments necessary to provide adequate
quality of service to the final customers under both timeframes.
Results were obtained based on a detailed model of the medium
voltage system produced in PSS®SINCAL starting from field
information on asset parameters and network topology. This model
also incorporated load measurements and our own estimations on
the likely load that will materialize in the system once the existing
generation restrictions are lifted, by the implementation of the
North East Power System of Afghanistan and by the addition of
new local generation. Figure 1 shows the Kabul model in PSS®SINCAL.
Siemens PTI also performed analysis of the 110 kV network with
the incorporation of 100 MW of diesel-fired generation located
to the north and east of the East Kabul substation.
Several new
substations were recommended, and the optimal location for each
was determined by: (a) defining a typical area of influence of
the new and existing substations as a function of feeder length
and load density, and (b) finding the load centers of the resulting
service areas selected, taking into consideration the location
of existing substations. The end result was a system served from
substations located close to all load centers.

Figure 1:
Kabul Model in PSS®SINCAL
Review and Planning of Belize Electricity Limited (BEL) Network
using PSS®SINCAL
This project delivered the results of the review and planning
conducted for the BEL distribution network (unbalanced network).
The initial network data obtained from BEL was in PSS®ADEPT
and had to be converted to PSS®SINCAL. The conversion, while
straightforward, required numerous changes to get the load flow
running in PSS®SINCAL. We appreciate the help received from
SimTec GmbH on this conversion process.
In this
project, we made use of all the powerful tools for network planning
which are available in PSS®SINCAL. Short descriptions of some
tools and functions we used are as follows:
Feeder
Function:
The Feeder function allows the user to analyze the electrical
network structure. (A feeder is a network supply area that leaves
from a substation.) The user can determine all feeders of the
network starting from specially designated nodes/busbars. Feeders
are determined by the tripping status of the network elements.
This means the current network operational status is being observed.
Load
Development:
The Load Development tool calculates load flow in distribution
networks, taking into consideration the load increase, power ratings,
and start-up and shutdown dates. This tool determines the load
in these networks at future times. These calculations are based
on a detailed network analysis.
ISO Areas:
The ISO Area tool can be used to determine the point of load center
based on load density. The point of load center is an important
piece of information for planning an installation of a new substation.
Figure 2
shows the BEL model in PSS®SINCAL.
In the review
and planning of the BEL network, Siemens PTI:
- Developed
a load forecast at the distribution level.
- Produced
an immediate to short term (2008 – 2012) distribution
plan that:
- Identified
a prioritized list of system upgrades necessary for delivering
power to final customers to maintain adequate quality of
service.
- Identified
those investments that are necessary to reduce technical
economic values.
- Recommended
required reactive compensation and capacitors.
- Analyzed
the upgrade of all the distribution networks to 22 kV and defined
the implementation strategy.

Figure
2: BEL Model in PSS®SINCAL
Distribution
Transformer and Low Voltage Network Optimization Study for BEL
using PSS®SINCAL
This work involved an efficient planning methodology to select
an optimal combination of transformer size and the LV network
conductor that would minimize the Life of Asset (LOA) costs, while
taking into account the voltage drop and the transformer loading
constraints for a period of 30 years including load growth. Using
different combinations of typical transformer size, triplex service
drop conductor and choice of network configuration, 200 study
cases were simulated in PSS®SINCAL. For each case, the cost
per kVA was calculated by dividing the LOA costs by the initial
loading capacity for each transformer. (The initial loading capacity
was preferred over the nominal rating as it takes into consideration
the possible loading limitations due to voltage drop.) Finally,
all network configurations were generalized based on load density,
and the coincident peak load per customer, and cost curves were
obtained for several possible combinations of transformer size
and triplex service drop conductor. The cost versus load density
curves were parameterized using trend line analysis for other
load densities which were not included in the list of study cases.
The optimal combination of transformer size and LV network conductor
was found by locating the combination that minimized the LOA costs
for several given densities. Figure 3 is a representation of that
study.
Figure
3: Representation of the Study for Selection of Optimal LV Network
Configuration
Ongoing Project:
Inventory, Review and Planning of the South San Joaquin
Irrigation District Distribution Network using PSS®SINCAL
Siemens PTI has assisted the South San Joaquin Irrigation District
(“the District,” in California) in the process of
inventorying and evaluating certain electric distribution assets
that they may wish to acquire. In 2004, after an inventory we
conducted for the District, we projected system expansions and
severance investments for 2008 and 2012. Since 2004, the distribution
system may have had important changes and it may have been expanded
and reinforced by Pacific Gas and Electric in a different way
than what was envisioned. Therefore, the District has asked Siemens
PTI to update this inventory and review the expansion plan as
necessary to reflect the 2008 configuration of the system. PSS®SINCAL
is used for review and expansion planning of this network. Figure
4 shows the South San Joaquin Irrigation District (SSJID) model
in PSS®SINCAL. The concentric circles in the figure indicate
the various radii of coverage of the substations.

Figure
4: SSJID Model in PSS®SINCAL
Download
document as .pdf
| Siemens Energy,
Inc., Power Distribution, T&D Service Solutions
Siemens Power Technologies International
400 State Street | P.O. Box 1058 | Schenectady,
NY 12301-1058
Privacy
& Legal |
|