Risk Assessment of Power Systems with PSS™E
Risk and
reliability are the two facets of a measure of the ability of
the electric power system to deliver electricity to all points
of utilization within accepted standards and in the amount desired.
Both terms have the same implication. Higher risk means lower
reliability, and vice versa. A general definition of risk is “probability
x consequence.” In power systems, this concept can be applied
to calculate certain reliability indices such as Expected Unserved
Energy (EUE) which is “probability x lost MW” (consequence)
and a measure on system reliability from customer point of view.
Risk assessment of
power systems can be performed using a deterministic or probabilistic
approach. The traditional deterministic methods for transmission
planning and power system security assessment in real-time for
system operations have been found to be inadequate in the new
deregulated environment as power systems present a probabilistic
behavior to some extent, such as random failures of equipment,
load growth forecast uncertainties, energy import and export transactions
on the volatile market, etc. Use of the probabilistic reliability
method complimentary to the deterministic method is getting more
and more attention in both system planning and operation. This
increasingly requires quantification of benefits as a result of
increased reliability or decreased risk.
The newly implemented
reliability features in Siemens PTI’s PSS™E employ
both deterministic and probabilistic reliability methods that
can be used for risk assessment of power systems in a deregulated,
competitive power market.
Methodology
The methodology used for risk assessment in PSS™E involves
two major components: deterministic contingency analysis and probabilistic
index computation (probabilistic reliability assessment) as shown
in Figure 1. Deterministic contingency analysis uses the enumerative
approach to evaluate each contingency and simulate sequences following
a contingency. Based on deterministic contingency analysis results,
outage statistics of contingencies are incorporated to calculate
various probabilistic indices including probabilistic indices
of overloads, voltage violations or voltage collapse, loss of
load, expected unserved energy (EUE), etc. These indices can be
used to measure weak points or risks in a system.
Figure
1 - Methodology of Risk Assessment in PSS™E
The deterministic contingency
enumeration process in PSS™E uses built-in contingency ranking
so that the user specified contingencies and automatically generated
contingencies from rankers can be evaluated individually or combined
with each other as multi-level contingencies as shown in Figure
2. It also features generation redispatch, non-divergent power
flow solution algorithm, tripping simulation and corrective actions
[1]. Probabilistic reliability assessment takes the results of
deterministic contingency analysis as inputs, matches each tested
contingency with its outage statistics and calculates the probabilistic
indices for a type of problem specified by the user, as shown
in Figure 3.

Figure 2 -
Automatic Multi-Level Contingency Analysis in PSS™E

Figure 3 - Probabilistic Reliability Assessment Function in PSS™E
Probabilistic Models
There are two probabilistic outage models: an independent single
element outage model and a multiple element outage model. An independent
single outage is the failure of one unique component, and is not
related in terms of its cause to any other failures that may occur
at the same time. For each component, frequency and duration of
the independent outage must be specified. The single element outage
is modeled using a binary-state model. At any time, the element
can be in one of two states: In Service (Available) and Outage
(Unavailable). The transition to the outage state is called failure,
and is assumed to occur at a constant rate,
, in failures per year; whereas the transition to the in-service
state is a restoration event, and is also assumed to
occur at a constant rate, ,
in restorations per year. The mean duration that the equipment
is in service is m years; while the mean duration that
it is out of service is r years. Thus, the probability
that the equipment is in service or out of service is:
Or 
And

The frequency
to transition from in service state to outage state is equal to
the frequency to transition from the outage state to the in service
state, and is given by:

The average duration that the element is in the Outage State is:

Multiple
element outages occurring simultaneously may come about in different
ways, e.g. from the same cause, or from independent causes for
each outage. Multiple element outages can be further divided into:
multiple independent outage, common mode outage as well as substation-related
outage or dependent multiple outage. The probability and frequency
of an independent multi-element outage event can be computed directly
from the frequencies and durations of the individual independent
outages. For example, given two independent outages, the parameters
of an equivalent double outage can be computed as follows:

And

And

where PA
and PB are the individual probabilities of
independent outages for elements A and B; FA
and FB are the respective frequencies of independent
outages for the two elements; and DA and DB
are the corresponding average durations in hours. The probabilities
and frequencies of common mode and substation-related outages
cannot be derived directly from the single element outage statistics.
These outage events must therefore be explicitly specified with
their corresponding frequency of occurrence and outage duration.
Probabilistic Index Computation
PSS™E uses contingency enumeration methodology to calculate
probabilistic indices. The base case and mutually exclusive contingency
cases form a state space of an electricity system as shown in
Figure 4. Each node represents an operation state: base case or
a contingency case. The sum of probabilities of all states is
equal to1. Probabilistic indices of system problems are computed
by identifying the set of states that satisfy failure criteria
and the transition rates from any state inside the set to a state
outside of the set. In the figure, a yellow node represents a
state that has violations; all yellow ones form the set S
containing states that satisfy failure criteria. Failure criteria
include branch overloads, bus voltages outside high or low limits,
bus change exceeding deviation criteria and loss of load.
Figure 4 - System State Space Diagram
For example:
the probability of system overload problems is calculated as:

where the
set S consists of all cases that cause
thermal overload problems, PiOUT is the probability
of state i. The frequency of system overload problems
is calculated as:

The total
frequency and probability are accumulative quantities for all
contingencies (single or multiple) resulting in the problems.
The duration is averaged for all failed contingencies. The composite
indices combining probability and system problems are defined
as [2]:
where Vi
is the sum of amount of violations (overloads, voltage violations,
loss of load, etc.); Pi is probability of
an outage event causing violations; and S
is the set of contingencies resulting in violations. The loss
of load in MW/year and EUE in MWh/year
measuring customer impacts are calculated as follows:


where mi is load loss for outage event i
(MW); fi is frequency for load loss caused
by outage event i (occurrence/year); di is
duration for load loss outage event i (h). These probabilistic
indices provide a better indication of power system reliability
by taking into consideration the relative likelihood of different
contingencies that may occur from system and customer standpoints.
Case Studies
Several reliability studies are performed with PSS™E on
the IEEE Reliability Test System (RTS) [3] as shown in Figure
5. In the RTS, a peak load of 3,563 MW and an installed generation
capacity of 4,764 MW are assumed. The transmission network consists
mainly of 230 kV and 138 kV voltages. The large generation is
located in the northern area and connected to 230 kV, and major
loads are in the south and connected to 138 kV. Power is transferred
from the north to the south via an interface comprised of 230
kV lines and 230/138 kV transformers.

Figure
5 - IEEE Reliability Test System
Application
1: Probabilistic Indices
A n-2 contingency analysis with tripping and corrective actions
initiated is performed for the RTS system. Some typical historical
outage data for major transmission equipment based on worldwide
historical data sources is used for probabilistic index calculation.
Table 1 shows a sample output of the probabilistic indices including
the frequencies and durations of load losses and EUE
as well as impact indices on individual bus and system-wide basis.
The probabilistic results can also be graphically displayed, e.g.
EUE indices on the impacted buses are displayed in red
numbers in Figure 5.

Table
1 - Probabilistic Indices of Loss of Load
Application 2: Weak Point Analysis
The probabilistic indices can be used to rank weak points in a
system to identify the components of the system that are experiencing
the most severe reliability problems. Figure 6 is a contour diagram
on the probability of the voltage problem at each bus; it clearly
shows that buses 224 and 103 are the most vulnerable parts in
the system and require voltage compensation to mitigate voltage
problems and improve system reliability.

Figure 6 - Contour Diagram on Probabilities of Voltage Problems
Application 3: Probabilistic Reliability Margin
In deterministic reliability studies, the reliability margin can
be defined as the maximum level of incremental power transfer
that the system can handle without experiencing any defined reliability
problems, e.g. n-1 compliance. The concept of deterministic reliability
margin can be extended by applying a tolerance threshold to determine
probabilistic reliability margin [2]. In the RTS system, power
transfer from the north to the south is changed incrementally
in the step size of 100 MW; both deterministic and probabilistic
reliability assessments are performed for each transfer level.
The probabilistic indices of voltage violations, overloads and
overall system problems are plotted as a function of the incremental
power transfer as shown in Figure 7.

Figure 7 - Probabilistic Indices and Reliability Margin with Power
Transfer
References
[1] Feng Dong and Baldwin P. Lam, “Bulk Electric System
Reliability”, Siemens PTI eNewsletter. Power Technology,
September 2006.
[2] Nicolas Maruejouls, Vincent Sermanson, Stephen T. Lee and
Pei Zhang, “Practical Probabilistic Reliability Assessment
Using Contingency Simulation”, Presented at the IEEE Power
Engineering Society's 2004 Power Systems Conference and Exposition,
New York, New York, 10-13 Oct. 2004.
[3] Reliability Test System Task Force Report, “IEEE Reliability
Test System”, IEEE Transactions on Power Apparatus and Systems,
Vol. PAS-98, No.6 November/December 1979.
Download document
as .pdf
| Siemens Power Transmission
& Distribution, Inc., Power Technologies International
1482 Erie Boulevard | P.O. Box 1058 | Schenectady,
NY 12301-1058
Privacy
& Legal |
|