Siemens PTI in Peru to Present Recommendations to Electric Sector Stakeholders Regarding Transmission Interconnection Solutions
Siemens
PTI (in association with Quantum Andes, a Peruvian firm) delivered
several presentations last November in Lima to Peruvian electric
power sector stakeholders. These presentations included recommendations
with respect to transmission interconnection reinforcement solutions
between the central and southern regions of Peru. The recommendations
were developed as part of an assignment performed by Siemens PTI
and Quantum Andes for Osinergmin (the energy and mining regulatory
entity in Peru) entitled "Risk Analysis of the Transmission Interconnection
between the Central and Southern Regions." Among the attendees
at the presentations were representatives from the Ministry of
Energy and Mines, Osinergmin, COES (the system operator) and REP
(a transmission service provider). The presentations also included
Siemens PTI's independent assessment of the current transfer capacity
between the central and southern regions, and the results of our
analysis of the Peruvian regulatory framework for electricity
relative to the implementation of new transmission projects.
The assignment
started in June of 2007 and was completed in November of 2007.
The Siemens PTI project team included Ramón Nadira, Nelson Bacalao,
Carlos Dortolina, Paloma De Arizón, Yuriy Kazachkov, Arthur Pinheiro,
and José Daconti. The Siemens PTI team that traveled to Lima for
the final presentations included Carlos Dortolina, Nelson Bacalao
and Yuriy Kazachkov. This project was a follow on to a previous
assignment entitled "Expansion and Planning Model of the Peruvian
Transmission System, 2006 - 2016," carried out between July 2006
and March 2007.
In both
of these projects Siemens PTI applied a planning under uncertainty
methodology known as trade-off risk, or TOR [1, 2]. TOR has been
proven to be very effective in multi-objective optimization problems
such as transmission planning. With multiple conflicting objectives,
the traditional concept of optimization is of limited use since
there is usually no plan which is "best" in terms of all of the
objectives or attributes of concern. Further, TOR is able to explicitly
consider structural uncertainties (e.g., those associated with
both the location and size of new generating power stations) to
produce robust transmission plans.
Key to the
successful application of TOR is the correct definition of options
(choices or possible decisions available to the planner), uncertainties
(quantities or events which are beyond the decision makers' foreknowledge
or control), and scenarios. This is shown in Figure 1. Scenarios
are assembled by combining specific options with futures (and
the latter are specific materializations of the modeled uncertainties.)
Scenarios are evaluated in terms of defined attributes.

Figure 1 - Planning Approach
The
central and southern regions of Peru are currently interconnected
by means of an approximately 610-km, series-compensated, double-circuit
(on the same tower) AC transmission line operating at 220 kV.
The line runs from the Mantaro substation in central Peru to the
Socabaya substations in the southern region of Peru. Series compensation
(and switching) are applied at Cotaruse, a mid-point substation.
Siemens PTI determined that the nominal transfer capacity of each
of the circuits was 550 MW. However, because of thermal limitations
on the series compensation devices - as well as dynamic stability
and other considerations - the double-circuit line is reported
to be operated only at a maximum transfer capability of 246 MW
(123 MW per circuit). Significant additional transfer capability
from the central to the southern regions is anticipated to be
needed, in light of the projected development of the generation
resources and the load demand in the country.
In order
to increase the transfer capability between regions, numerous
transmission expansion options were considered, including several
based on HVDC or HVAC technologies. After significant discussions
about the merits of each postulated option (including the required
timeframe for implementation), a total of six plans were agreed
upon, as follows: (i) Plan A: increase the capacity
of the existing line by enhancing the thermal capability of its
series compensation devices (hereafter this is referred to as
"additional series compensation", (ii) Plan B:
build a new AC 220 kV line plus additional series compensation,
(iii) Plan C: build a new HVDC line plus additional
series compensation, (iv) Plan D: install thyristor-controlled
series compensation (TCSC), (v) Plan E: install
a new AC 500 kV line plus additional series compensation (this
plan also required the installation of a flow control device,
such as a phase-shifter), and (vi) Plan F: install
a new HVDC Back-to-Back ("B2B") converter station at the Cotaruse
substation. Plan F was eliminated in the next stage of the analysis,
as it was found to be very much inferior to the other plans.
As alluded
to above, these plans were combined with uncertainties to form
scenarios. The uncertainties that were considered in the analysis
included, size, timing and location of future generating power
plants, load demand growth ratios (by region), fuel costs, cost
of energy not served, and hydrology. Uncertainties were modeled
using an unknown-but-bounded approach [1, 2], which assumes upper
and lower limits on the uncertainties, with no presumption about
their probability distributions.
A total
of 135 scenarios were modeled and compared in terms of the following
attributes: (1) capital investment costs, (2) operations and maintenance
costs, (3) cost of unserved energy, (4) system losses, (5) system-wide
locational marginal prices of energy, (6) final end-user price,
and (7) NDH and MIF, two non-traditional probabilistic planning
criteria defined by Siemens PTI as part of the previous transmission
expansion project performed for Osinergmin. NDH, or Hours of Non-economic
Dispatch, measures the number of hours the transmission system
constrains the economic dispatch of generation. MIF, or MWh of
Interrupted Flows, measures the MWh of flows that are interrupted
due to limitations in the transmission system. Numerous system
simulation runs were performed to determine the value of each
of these attributes for each scenario. These simulations were
made using PSS™E - Siemens PTI's proprietary program for simulating,
analyzing, and optimizing power system performance - as well as
a market simulation program developed by Osinergmin specifically
for the Peruvian system (known as PERSEO).
Below we present a sample of the graphical results
of our analysis. Figure 2 shows several scenarios (not all) plotted
for two attributes: Net Present Value (NPV) of total costs and
NPV of final end-user prices (all in USD/MWh). Even though there
are some scenarios very close to the origin (0,0), further analysis
showed that the corresponding plan (i.e., Plan A) is robust for
some materializations of uncertainties, but it is extremely volatile
in case different materializations of uncertainties occur. This
can be better explained through Figure 3, which shows the results
obtained for the NPV of total costs for several materializations
of the uncertainty associated with load growth (i.e., high, average,
and low). This figure shows that Plans A and D can potentially
have either the lowest or highest regret levels. For example,
if one chooses Plan A and the load grows at a high rate, then
the level of regret is extremely high. On the other hand, if one
chooses Plan C and the load grows at a low rate, then the level
of regret is relatively low.

Figure 2 - Trade-Off Risk Analysis
Results

Figure 3 - Minimum Regret Analysis.
Results for the NPV of Total Costs
As
is usually the case, our analysis showed that no plan was the
preferred one for all possible materializations of the uncertainties.
That is, no plan was robust. We then proceeded
to apply what is known as the MiniMax approach (i.e., to minimize
the maximum regret). Regret in the context of this analysis is
defined as the difference between the outcome for the option one
chooses, and the best outcome one would obtain for a given future.
Hedging strategies were also designed for protection in case certain
credible futures would materialize the "wrong way."
The solution
recommended in this study was to immediately reinforce the existing
double circuit line by enhancing the thermal capability of its
series compensation devices, and to initiate the development of
a parallel high voltage circuit between Mantaro and Socabaya whose
optimal timing was recommended to be a function of the evolution
of the generation and load demand in the country in the next few
years.
During the
presentations, Osinergmin and the various other stakeholders focused
intensely on short term concerns relative to the existing interconnection.
These concerns, and equally importantly, the long term concerns,
were shown to be properly addressed by our methodology. All in
all, the stakeholders were very vocal regarding their satisfaction
with the depth and thoroughness of the analysis performed by Siemens
PTI.
Finally,
it is important to mention that as a direct result of the two
projects described earlier, Osinergmin is reportedly considering
to issue orders to the effect that: (1) TOR is the preferred methodology
to be applied for planning transmission expansions in Peru, and
(2) CIM/XML is the basis for the standard data base of power system
simulation data to be adopted in Peru.
References.
[1] Nadira, R., R.R. Austria, C.A. Dortolina, and M.A. Avila,
"Transmission Planning Today - A Challenging Undertaking", The
Electricity Journal, Elsevier, Inc., Vol. 17, No. 4, May, 2004,
pp. 24-32. [2] Schweppe, F.C., H.M. Merrill, and W.J. Burke, "Least
Cost Planning: Issues and Methods," Proceedings of the IEEE, Vol.
77, No. 6, June 1989.
Download
document as .pdf
| Siemens Power Transmission
& Distribution, Inc., Power Technologies International
1482 Erie Boulevard | P.O. Box 1058 | Schenectady,
NY 12301-1058
Privacy
& Legal |
|